Heavy Duty Professional Kran Gießen Schöpfkellen für Gießerei
Produktbeschreibung
Introduction |
Casting bridge cranes are the main handling equipment for smelting workshop of steel works. They are used for conveying, pouring and hot metal in smelting process. |
Construction |
bridge, main crab, auxiliary crab, connecting traverse,trolley traveling mechanism and electric part. |
Main beam |
The trolley traveling mechanism and main electric equipment are installed in the girder. The girder’s electric panel room employs rock wool for heat insulation, and has an air cooler inside. To reduce heat radiation of molten steel to metal structural members, a thermal baffle is set along the span direction at the bottom of the girder. |
Drive |
The trolley traveling mechanism adopts four-corner drive. |
Painting |
anti-rust painting,Primer and finishing paint,yellow or red color, General thickness:about 105microns |
Equipment |
The crane is equipped with a special electric scale, and there are display devices in the cab and on the bridge. The main hoisting mechanism is furnished with an over-speed switch. |
Heavy duty professional crane pouring ladles for foundry | ||||||||||
Lifting capacity(t) |
125/32 |
140/32 |
160/32 |
180/50 |
200/50 |
225/65 |
240/80 |
280/80 |
320/80 |
|
Working class |
A7 |
|||||||||
Span(m) |
19 |
19 |
27 |
28.5 |
28 |
27 |
22 |
22 |
24.5 |
|
Lifting height(m) |
Main hook |
24 |
22 |
25 |
27 |
26 |
32 |
25 |
29 |
28 |
Auxiliary hook |
26 |
24 |
26 |
29 |
26 |
34 |
27 |
29 |
32 |
|
Speed
|
Main hook |
7.6 |
7.8 |
9.8 |
7.5 |
6 |
11 |
7 |
12 |
7.5 |
Aux. hook |
9.7 |
9.7 |
12 |
10 |
10 |
11 |
9.6 |
10 |
10 |
|
Main trolley |
38 |
36 |
43.5 |
40 |
41 |
41 |
35 |
40 |
29 |
|
aux.trolley |
39 |
37.5 |
43.5 |
38 |
38 |
39.5 |
38 |
40 |
39 |
|
crane |
76 |
73 |
84 |
80 |
78 |
84 |
80 |
80 |
58 |
|
Max wheel load(KN) |
505 |
535 |
485 |
525 |
530 |
550 |
545 |
735 |
750 |
|
Steel track recommended |
QU120 |
|||||||||
Power source |
380V 50HZ 3-phase A.C. |
Produktgruppe : Laufkran-Serie > Castingkran